Weekly Report – Fort McMurray, Alta.

August 15, 2017

It’s been another extremely busy week in Fort McMurray as we only have a few short weeks to finish up the houses and welcome the homeowners back into their new homes.

We moved lots of dirt this week in order to finish getting the Hardie panel skirting on to the houses. Most of the basement windows were installed (leaving one open at each home for access to pour the basement floors next week).

We have all the railings on the porches and the stairs on all three homes. Volunteers have begun the tie downs of our homes along with rim joist insulation.  All of the underground plumbing and electrical have been completed and the homeowners are making arrangements for power to be brought into their homes.

We are looking forward to the basement floors getting poured next week. We anticipate another full week of good labour for the Lord.

This week we welcomed another crew from World Renew to help with the work here in Ft. McMurray.

From the Ft. McMurray Long Term group: Robert, Sally, Emily & Nicholas and our World Renew volunteers.