Saipan, N.M.I. – Weekly Report – Dec 2-6, 2019

December 11, 2019

Work on the Saures house is progressing nicely. The entire house has been covered in tin and securely fastened with enough hurricane clips to last through almost anything. We will finish off the outside kitchen and electrical repairs next week.

With the rest of the crew coming in on Monday we have another project lined out to begin on Monday. Delthina’s house has no roof so will be an easy repair.  Windows and two doors will need to be installed. As we progress on Delthina’s and finish Saures’ home I will look for a third project that I would like to have finished before we leave in December.

If the weather holds we should have three families into homes when we leave the island.

Steve & Dee Bell, Project Director & Office Manager