Ponce, Puerto Rico, Weekly Report, Aug 19-25, 2018

September 7, 2018

This week, we had four volunteers from Philadelphia: Nes Espinosa, Carlos Garcia Torres, Hector Marrero, and Vandy Parks. We laid the floor tile, wired up the house, and installed ceiling fans and lights. We installed the exterior doors and purchased the kitchen counter. We completed plastering the exterior and primed it, and we nearly finished painting it.

This next week will be our last week here, so we are hoping to tie up as many loose ends as possible, such as installing the kitchen, finishing the plumbing, hanging the porch ceilings, finishing the exterior paint, cleaning up the jobsite, etc.