Pollocksville, NC – Weekly Report – Nov 9-13, 2020

November 16, 2020

We were blessed with three men from Virginia, two from Pennsylvania, and a lady from Ohio this week.

There was much painting done at the Murphy house and then the crew started the flooring.

At the Plantation house kitchen cabinets and countertops were installed, the painting was finished, and closet doors installed. On Friday the ladies did the deep cleaning and this project is completed.

We started a new project at Okla’s house in Maysville where we needed to strip two bedrooms to the studs to get rid of mold. We will be returning to insulate and drywall these rooms as well as some other repairs.

We also returned to Shirley’s house where we painted doors and trim.

A new office manager and mitigation manager arrived to replace the current ones whose terms were completed.

For the long term staff: Jay, Dennis, Mildred, John, Rita, Margaret, Emanuel, Sue, and Tim