Meridian, MS – Weekly Report – Mar 4-8, 2019

March 13, 2019

This week we had a group of six guys from Pennsylvania and two couples from Michigan.  They possessed excellent skills that matched our needs.

At Ms. Monica’s the crew finished the drywalling and painting.  Floors were prepared for flooring, which was installed and completed just as quitting time came on Friday.

The second crew spent their week at Ms. Flora’s home.  Painting was finished and the kitchen cabinets, including countertop and sink, were installed.  Interior doors were installed as well as some trim.  This home is very near completion.

From all the volunteers at Meridian