Conway, SC – Weekly Report – July 29-Aug 2, 2019

August 7, 2019

We had two groups at the project this week – a youth group from Vincent Mennonite in Pennsylvania and a smaller group from Marietta Community Chapel, also from Pennsylvania. In addition we also had a mother and her adult son working with us.

This was the last week the Conway project was open so we spent time finishing up houses and also work to close the site.

All job cards were signed off this week! Progress this week:

  • Frazier – painted doors, trim, doors, outside, baseboard and window frames; installed top cabinets and countertop; installed door frames and bifold doors
  • Jimetta Sherman – put in base cabinets, installed countertop
  • Tonger Sherman – replaced bad floor; installed some drywall; mudding and taping
  • Doctor – built handicapped-accessible ramp
  • Charlie Sherman – built outside railing

We also did final touch ups and last details at the Huggins, McCray, and Bellamy houses.