Monday, at an MDS site, can be confusing at times. We had some volunteers finishing steps and porches and another group finished sheeting interior walls. Two other volunteers were hauling trim and doors to another site.

Tuesday, one group started putting up rafters. One group finished the flooring and hung some doors and one group was building on porches.

Wednesday, they put blocking on rear rafters and placed the corner rafters. They also finished putting up the porch beams. Another group finished hanging doors and all the windowsills, while another group was still building the porch and adding the ramp.

Thursday, we had the one group still working on the porch and ramp. The other group was putting up house wrap, and front rafters and another group was putting on trim and installing cabinets.

Friday started out as a very warm day. The group that was putting up rafters found it very warm, but the rafters are up. The other group installed trim, put in counter tops.

We, the long-term team, would like to thank all the people that have come to serve this week. May God Bless You!

Submitted by: Don, Ryan, Peter & Margaret, Dan & Pam Wiebe and family, Helen and Eva