Coastal Bend, TX – Weekly Report – Dec 9-13, 2019

December 17, 2019

Our week started of with 14 volunteers. Monday was a very hot day, but that didn’t keep our volunteers from working. One group was putting siding and rafters on a shed. One group was putting up exterior walls and putting on hurricane straps and another was building a ramp and started on the steps.

Tuesday, they finished framing interior walls and started sheeting the south wall. The people on the shed were sheeting the roof and installing a door. The ramp people were putting up ramp boards and steps. Today was a cold, rainy kind of day.

Wednesday was our last day of working on the sites. It was still cool but no rain. The people on the shed finished the shed. The people on the ramp finished the ramp and steps. The people on the house finished sheeting the house.

Praise be to God for a great week!

Submitted by: Don, Ryan, Peter & Margaret, Eva, Dan & Pam and family